Department of Parks and Recreation

 

Reference:                      Approving procurement of 24-008442 Cherry Meadows Park Construction

 

To:                                                               Mayor Gregory Mills

 

Through:                                          Michael P. Martinez, City Manager

Prepared By:                                          Kyle Sylvester, Assistant Director of Parks and Open Space                                          

Date Prepared:                     January 31, 2024

 

PURPOSE

To request City Council approval for the procurement of the 24-008442 Cherry Meadows Park Construction Project by awarding a contract to Elite Industries, Inc., deemed the most responsive and responsible bidder of the four (4) bids received in response to the published solicitation, and approving the resolution giving the City Manager, or designee, authority to sign the contract.  Per City Code Section 3-8-30(b): “All materials, services, and construction contracts, except as otherwise provided in this Article, with an estimated cost greater than one hundred thousand dollars ($100,000.00), shall be awarded through the formal solicitation procedure or the formal RFP process by the City Council.  After due notice inviting bids, purchase orders and contracts shall be awarded to the lowest, responsive and responsible bidder.

 

BACKGROUND

 

Cherry Meadows is an undeveloped 4.38-acre site that is designated for park use. This site will serve as a neighborhood park for the surrounding community. Construction will include water-wise landscaping, playground, loop trail that connects to the neighborhood and the regional trail along the south edge of Baseline Road, shelter, irrigation, picnic tables, dog stations, and other park amenities. 

 

Sustainability:
The park will have both bluegrass and native grass components for water conservation

 

FINANCIAL IMPACT

 

Sufficient appropriation exists for this project.

 

STAFF RECOMMENDATION

 

Staff recommends that the City Council approve the request to issue and to award Elite Industries as the most responsive and responsible bidder.

 

ATTACHMENTS