Legislation Details

File #: ID-298-26    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 10/7/2026 In control: City Council
On agenda: 10/20/2026 Final action:
Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, APPROVING AN AMENDMENT WITH DHM DESIGN CORPORATION FOR THE SPORTS COMPLEX DESIGN SERVICES PROJECT IN THE AMOUNT OF ONE HUNDRED SEVENTY THOUSAND FOUR HUNDRED NINETY DOLLARS ($170,490), AND AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE THE AMENDMENT ON BEHALF OF THE CITY
Attachments: 1. Reso 26 - Amednment 1 DHMDesign Corp_Sports Complex Design, 2. Sports Complex Design Services - City Council Meeting 10-20-2026
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department of Parks
Reference: Amendment No. 1 to the Contract for theSports Complex Design

To: Mayor Gregory Mills and Members of City Council
Through: Michael P. Martinez, City Manager
Prepared By: Kelsey Archuleta, Procurement & Contracts Manager, and Ryan Smith, Parks Planning, Development and Grant Manager
Date Prepared: September 23, 2026
PURPOSE
Requesting City Council’s approval to amend the contract 24-008466 for Sports Complex Design Services, and approving the resolution granting the City Manager, or designee, authority to sign the amendment.  Per City Code Section 3-8-170, “All change orders or amendments shall be processed through the Finance Department. Department directors shall have authority to approve individual amendments or change orders up to the department director’s aggregate signing authority for the total contract price. The City Manager shall have the authority to approve individual amendments or change orders, in the aggregate, up to the City Manager’s signing authority or up to ten percent (10%) of the original contract amount, whichever is higher. All other amendments or change orders shall be approved by the City Council, as appropriate, based on the signing authority established in this Article.”

BACKGROUND
In April 2024, City Council approved a contract with DHM Design Corporation for $932,212.00 to complete the design for the proposed sports complex at Southern Street and South 40th Avenue.

Design work has been underway since that time. After the 65% design submittal, the construction cost estimate exceeded the initial projections. To bring the project back within the construction budget, the City directed DHM Design Corporation to lead a value engineering effort. This process included adjusting amenities and expanding the site by approximately 7.5 acres to the south on City owned property. These changes reduced costs related to grading, stormwater infrastructure, roadway impacts, and other site related work, while still mai...

Click here for full text