File #: ID-526-20    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 11/5/2020 In control: City Council
On agenda: 11/17/2020 Final action:
Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACCEPTING THE BID OF ARROW J LANDSCAPE & DESIGN, INC. AND APPROVING THE PROCUREMENT OF DESIGN BUILD BASKETBALL COURT AND TRAIL, PROJECT #20-006484, TO ARROW J LANDSCAPE & DESIGN, INC. FOR THE CONTRACT AMOUNT OF ONE HUNDRED FIFTY THOUSAND DOLLARS ($150,000), AND AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE AND SIGN THE CONTRACT ON BEHALF OF THE CITY AND THE CITY CLERK TO ATTEST THERETO
Attachments: 1. Donelson BB Court Resolution, 2. Donelson BB Court PowerPoint, 3. 526 PPT

Department of Finance - Division of Procurement & Contracts, Department of Parks and Recreation

Reference:   Approving the procurement of 20-006484 Design Build Basketball Court and Trail

 

To:                                                               Mayor Gregory Mills and Members of City Council

Through:                     Jane Bais DiSessa, City Manager

                     Marv Falconburg, Assistant City Manager

Prepared By:                     Amber Gibbs, Procurement & Contract Manager, and Troy Channell, Parks Manager

Through:                                          Travis Haines, Director of Parks and Recreation

Date Prepared:                     10/21/2020

PURPOSE
Requesting City Council approval of formal solicitation for project # 20-006484 Design Build Basketball Court and Trail to the most responsive and responsible bidder, and approving the resolution giving the City Manager, or Designee, authority to sign the contract.  Municipal Code Section 3.08.090, “…All bids and proposals in excess of $50,000 shall be awarded through formal written procedures by the City Council.” 

 

 

BACKGROUND/HISTORY

Formal Proposals were requested from qualified professionals for the Design Build Basketball Court and Trail.  The work to be completed includes the design and construction of a new post tension concrete basketball court and the construction of a new concrete trail connecting the existing trail to a future parking lot at Thomas Donelson Park.  The original plan for Thomas Donelson Park included an area for a basketball court to be added in the future providing the park users with an additional amenity to the site.

The formal proposals were received on October 14th at 10:00 AM; three (3) firms submitting a proposal for the project.  All proposals were reviewed by the Parks and Recreation Department.

The three (3) firms submitting proposals are:

Arrow J Landscape & Design, Inc.

Colorado Designscapes, Inc.

ECI Site Construction-HAROD COPLAN MACHT

 

FINANCIAL IMPACT

Sufficient appropriation exists for the project.

 

 

 

 

 

 

 

STAFF RECOMMENDATION

It is recommended by Procurement & Contracts and the Parks & Recreation Divisions that the City of Brighton award the contract for the subject project in the amount of One Hundred Fifty Thousand Dollars ($150,000) to the lowest responsive and responsible bidder of Arrow J Landscape & Design, Inc.

 

 

OPTIONS FOR COUNCIL CONSIDERATION

Ø                     Approval as presented 

Ø                     Reject

Ø                     Require new proposals be prepared

 

Attachments:

Ø                     Resolution

Ø                     Bid Abstract