Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, APPROVING THE PROCUREMENT OF 2022 TRANSPORTATION PRESERVATION AND IMPROVEMENTS PROJECT, PROJECT # 22-007315, AND AWARDING A CONTRACT TO A-1 CHIPSEAL COMPANY FOR THE CONTRACT AMOUNT OF THREE MILLION NINE HUNDRED EIGHTY-SEVEN THOUSAND SEVEN HUNDRED EIGHTY-THREE DOLLARS ($3,987,783.00), AND AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE THE CONTRACT ON BEHALF OF THE CITY
Attachments: 1. Resolution Bid Acceptance 22-007315 Transportation Preservation and Improvements Project 2022.05.pdf

Department of Public Works

Reference: Approving the contract 22-007315 Transportation Preservation and Improvements Project                     

 

To:                                                               Mayor Gregory Mills and Members of City Council

Through:                                          Michael Martinez, City Manager

Prepared By:                                          Christopher Montoya, Assistant Director of Public Works

Date Prepared:                     May 13, 2022

PURPOSE

Requesting City Council approval for procurement of 22-007352 2022 Transportation Improvements Project, and to award a contract to A-1 Chipseal, Company, deemed the most responsive and responsible bidder of the one (1) response received from the posted solicitation. Per City Code Section 3-8-90: “[a]ll materials, supplies, equipment, service and construction contracts, except as otherwise provided in this Article, with an estimated cost of greater than fifty thousand dollars ($50,000.00), shall be awarded through the formal bid process or the formal RFP process by the City Council. After due notice inviting bids, purchase orders and contracts shall be awarded to the lowest responsive and responsible bidder.”

 

STRATEGIC FOCUS AREA

Safe, Active and Engaged Community

Financially Responsible

Supportive, Sustainable Infrastructure

 

BACKGROUND

The City of Brighton Public Works Department conducts annual projects for street repairs, maintenance, and improvements. Construction will primarily consist of installing asphalt pavement seal coats ranging from slurry seal to hot chip and including chip seal, subgrade preparations, pavement markings, milling, patching, striping, concrete sidewalk, ADA curb ramps, and all other work associated to complete the project. Additionally, the project consists of enhancing pedestrian and multi-modal infrastructure, improving ADA access, adding bike lane striping and signage, and traffic calming features.

 

FINANCIAL IMPACT

Sufficient appropriation exists for the project.

 

STAFF RECOMMENDATION

Staff recommends that the City Council approve the request to award the contract to A-1 Chipseal, Company as the lowest, and most responsive and responsible proposer.

 

OPTIONS FOR COUNCIL CONSIDERATION

Ø                     Approve as presented 