Skip to main content
File #: ID-41-26    Version: 1 Name:
Type: Informational Report Status: Agenda Ready
File created: 1/29/2026 In control: City Council
On agenda: 2/10/2026 Final action:
Title: Utility Repair and Construction: Master Price Agreement Awards
Attachments: 1. MPA- Utilities Maintenance and Operation Supplies Award- SS Presentation_Final
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Department of Utilities

Reference:                     Utility Repair and Construction: Master Price Agreement Awards

 

To:                                                               Mayor Gregory Mills and Members of City Council

Through:                                          Michael P. Martinez, City Manager

Prepared By:                                          Scott Olsen, Director of Utilities

Date Prepared:                     January 21, 2026

PURPOSE
Requesting City Council’s consideration for the procurement of 25000418M.1 As-Needed Utility Repair and Construction Services by awarding, at a future City Council meeting, a Master Price Agreement to American West Construction, LLC, CL Water Solutions, Inc., and Timber Wolf Excavating, LLC. These three were deemed the most responsive and responsible proposers of the seven (7) proposals received in response to the published solicitation. Per City Code Section 3-8-180, “Master price agreements with an annual not to exceed price of five hundred thousand dollars ($500,000.00) or less may be approved by the City Manager. Master price agreements with an annual not to exceed price greater than five hundred thousand dollars ($500,000.00) shall be approved by the City Council. After the City Council has approved a master price agreement, the City Manager may approve an annual extension and any amendment thereto, provided the contractor has performed the work satisfactorily, all terms and conditions of the contract have been fulfilled, the funds for said extension and amendment have been appropriated, and the annual not to exceed dollar amount of said extension or amendment has not increased from the original master price agreement.”

 

BACKGROUND

City staff are tasked with numerous maintenance, operation and construction activities annually, some of which extend beyond the abilities of the City’s equipment and expertise. In order to ensure continuity of operations, contracted vendors with specialized equipment/expertise are required to perform certain tasks. Examples of such tasks include:

                     Excavation to depths outside City equipment ability

                     Excavations that include complex dewatering operations due to groundwater

                     Installation of pipe/materials that cannot be moved by City equipment

                     Repairs to critical infrastructure

                     Installation of large extents of new piping

 

At times, these services are needed in emergency situations that require quick response times. The vendors selected for award have made it clear they can respond as outline in the Request for Proposals.

 

Master Price Agreements are used to effectuate the above tasks and respond to emergency situations.

 

FINANCIAL IMPACT

Sufficient appropriation exists in the Utilities operating budgets for as-needed and emergency maintenance and construction activities.

 

STAFF RECOMMENDATION

At a future City Council meeting, accept the three lowest, most responsive and responsible fee schedules and proposals of those received and approve new Master Price Agreements with American West Construction, LLC, CL Water Solutions, Inc., and Timber Wolf Excavating, LLC, each for an annual not to exceed amount of $2,000,000.

 

ATTACHMENTS

                     PowerPoint presentation