File #: ID-229-25    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 9/19/2025 In control: City Council
On agenda: 10/7/2025 Final action:
Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, APPROVING CHANGE ORDER NUMBER 1 WITH ENGINEERING ANALYTICS, INC. FOR THE LUPTON MEADOWS RESERVOIR DESIGN SERVICES PROJECT IN THE AMOUNT OF SIXTY-THREE THOUSAND THREE HUNDRED SEVENTY-FOUR DOLLARS ($63,374), AND AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE THE CHANGE ORDER ON BEHALF OF THE CITY
Attachments: 1. Reso 25 - Change Order 1 Lupton Meadows Reservoir Design Services, 2. Lupton Meadows Reservoir Design Services Change Order #1 - CC Presentation_Final
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Department of Utilities

Reference:                     CHANGE ORDER 1 WITH ENGINEERING ANALYTICS, INC. FOR THE LUPTON MEADOWS RESERVOIR DESIGN SERVICES PROJECT

 

To:                                                               Mayor Gregory Mills and Members of City Council

Through:                                          Michael P. Martinez, City Manager

Prepared By:                                          Scott Olsen, Director of Utilities

Date Prepared:                     September 12, 2025

 

PURPOSE
Requesting City Council’s approval of Change Order #1 to the Lupton Meadows Reservoir Design Services contract between the City of Brighton and Engineering Analytics, Inc. in the amount of $63,374. The resolution further requests City Council’s approval for the City Manager to execute any future change orders, in the aggregate, of 5% of the contract amount. Future change orders are not anticipated at this time, however, this is a complex engineering design project.

 

BACKGROUND

A design services contract was awarded to Engineering Analytics, Inc. in the amount of $496,894 in July of 2024. The contract is for the design of a pump station, bank protection and spillways for the Lupton Meadows Reservoir complex in Fort Lupton, CO. The City Manager was authorized to sign this contract due to the amount.

 

Additional design services are needed for the project and include additional geotechnical engineering, subsurface utility engineering and roadway design for County Road 25. Approximately half of the change order can be attributed to the roadway design that has been required by the City of Fort Lupton, CO.

 

FINANCIAL IMPACT

Sufficient appropriation exists in the Utilities Capital Improvement budget allocated to this project. The financial impact of these construction services has always been anticipated and accounted for accordingly in the overall Water Fund budget.

 

STAFF RECOMMENDATION

City staff recommend the City Council approve the resolution authorizing the City Manager, or designee, to execute Change Order #1 to the Lupton Meadows Reservoir Design Services contract on behalf of the City

 

 

 

 

OPTIONS FOR COUNCIL CONSIDERATION

                     Approve resolution as drafted

                     Approve a modified resolution

                     Deny resolution

                     Provide further direction to staff

 

ATTACHMENTS

                     Resolution

                     PowerPoint presentation