Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACTING BY AND THROUGH ITS WATER ENTERPRISE, ACCEPTING THE PROPOSAL OF EDGE CONTRACTING, AND AWARDING THE CONTRACT FOR THE ERGER’S SPILLWAYS AND SLOPE PROTECTION PROJECT TO EDGE CONTRACTING, IN AN AMOUNT NOT TO EXCEED THREE MILLION, TWO HUNDRED AND EIGHT THOUSAND, ONE HUNDRED TEN DOLLARS ($3,208,110.00), AND AUTHORIZING THE MAYOR TO SIGN THE CONTRACT ON BEHALF OF THE CITY AND THE CITY CLERK TO ATTEST THERETO.
Attachments: 1. Ergers Rip Rap Resolution, 2. Copy of Ergers Spillway and Riprap Bid Summary, 3. Council Presentation CB Draft 5-29-18 Animation

 

Body

Department of Finance - Division of Procurement & Contracts

Reference:                         A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACTING BY AND THROUGH ITS WATER ENTERPRISE, ACCEPTING THE PROPOSAL OF EDGE CONTRACTING, AND AWARDING THE CONTRACT FOR THE ERGER’S SPILLWAYS AND SLOPE PROTECTION PROJECT TO EDGE CONTRACTING, IN AN AMOUNT NOT TO EXCEED THREE MILLION, TWO HUNDRED AND EIGHT THOUSAND, ONE HUNDRED TEN DOLLARS ($3,208,110.00), AND AUTHORIZING THE MAYOR TO SIGN THE CONTRACT ON BEHALF OF THE CITY AND THE CITY CLERK TO ATTEST THERETO.

 

 

To:                                                               Mayor Kenneth J. Kreutzer and Members of City Council

 

Through:                                          Philip Rodriguez, City Manager

 

Prepared By:                                          Curtis Bauers, Director of Utilities

                                                               

Date Prepared:                     May 22, 2018

 

 

PURPOSE

Requesting City Council approval of a formal solicitation for the Erger’s Reservoir Spillways and Slope Protection Project to the most responsive and responsible bidder, and approving the resolution giving the Mayor authority to sign the contract.  Municipal Code Section 3.08.090, “. . . . All bids and proposals in excess of $50,000 shall be awarded through formal written procedures by the city council.” 

 

Strategic Focus Area

This project addresses needs in the City Council’s strategic focus area of Supportive and Sustainable Infrastructure. 

BACKGROUND/HISTORY

The Erger’s Reservoir is currently suffering from both erosion of its slopes and susceptibility to damage from periodic flooding. In order to combat this and protect the City’s assets the Utilities Department has had a design prepared to armor the upper two-thirds (2/3) of the slopes to protect them from erosion and install two spillways that will allow flood waters to pass through controlled locations that are built to handle those flows. Work shall include:

 

                     Installation of approximately 15,200 CY of rip rap on the slopes of Erger’s Reservoir

                     Installation of two (2) spillways

                     Installation of a grouted access ramp

                     Delivery of approximately 930 CY of rip rap to be used by the Urban Drainage and Flood Control District to protect the jetties in the South Platte River

 

 

Seven (7) formal bids were received on May 14, 2018 at 2:00 PM.  The proposals were received by the Procurement group and then transferred to the Utilities Engineering group for review.

 

 

Firms submitting proposals:

 

Ø                     ZAK DIRT, INC.

Ø                     CONCRETE EXPRESS, INC.

Ø                     SEMA CONSTRUCTION

Ø                     COLT & STEEL CORP

Ø                     FRONTIER ENVIROMENTAL SERVICES

Ø                     TEZAK HEAVY EQUIPMENT

Ø                     EDGE CONTRACTING

 

FINANCIAL IMPACT

Sufficient funding was approved in the 2018 budget for water resource projectsThe proposal from Edge Contracting is within the budgeted amount.

 

STAFF RECOMMENDATION

In completing the review and evaluation of this bid the recommendation is to award to the lowest most responsive and responsible bid of Edge Contracting in the amount of a total not to exceed three million, two-hundred eight thousand, one-hundred dollars ($3,208,110.00). 

 

Edge Contracting is in good standing with the State of Colorado.

OPTIONS FOR COUNCIL CONSIDERATION

Ø                     Approval as presented 

Ø                     Reject

Ø                     Require new bids be prepared

 

Attachments:

Ø                     Resolution

Ø                     Bid Abstract