Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACCEPTING THE PROPOSAL OF JR ENGINEERING, LLC TO DESIGN WATER LINES FOR FIRE FLOW FOR THE CONTRACT AMOUNT OF THREE HUNDRED THIRTY-EIGHT THOUSAND ONE HUNDRED NINETY-ONE DOLLARS ($338,191.00) AND AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE THE CONTRACT ON BEHALF OF THE CITY
Attachments: 1. Resolution - JR Engineering, 2. Council Presentation - Core City, 3. 245 PPT
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Department of Utilities

Reference:                     Approving the procurement of 22-007360 Core City Waterline Design                     

 

To:                                                               Mayor Gregory Mills and Members of City Council

Through:                                          Michael Martinez, City Manager

Prepared By:                     Kelsey Archuleta, Procurement & Contracts Manager

                                   Marc Johns, Interim Utilities Director

 

Date Prepared:                     Thursday, July 14, 2022

 

PURPOSE

Requesting City Council’s approval of the procurement of 22-007360 Core City Waterline Design by awarding a contract to JR Engineering, deemed the most responsive and responsible bidder of the seven (7) bids received in response to the posted solicitation, and approving the resolution giving the City Manager, or designee, authority to sign the contract.  Per City Code Section 3-8-90, “All materials, supplies, equipment, service and construction contracts, except as otherwise provided in this Article, with an estimated cost of greater than fifty thousand dollars ($50,000.00), shall be awarded through the formal bid process or the formal RFP process by the City Council. After due notice inviting bids, purchase orders and contracts shall be awarded to the lowest responsive and responsible bidder.”

 

STRATEGIC FOCUS AREA

Innovative

Financially Responsible

Supportive, Sustainable Infrastructure

 

BACKGROUND

The purpose of this project is to design the replacement of deteriorated and failing lines which have reached the end of their useful life with new infrastructure to accommodate added growth within the city while maintaining necessary fire flow requirements.

 

FINANCIAL IMPACT

Sufficient appropriation exists for the project.

 

STAFF RECOMMENDATION

Staff recommends that the City Council approve the request to issue an award to JR Engineering as the lowest, most responsive and responsible proposer. 

 

OPTIONS FOR COUNCIL CONSIDERATION

Ø                     Approval as presented 

Ø                     Reject

Ø                     Require new proposals be prepared

 

Attachments:

Ø                     Resolution

Ø                     Presentation