File #: ID-343-23    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 10/5/2023 In control: City Council
On agenda: 10/17/2023 Final action:
Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACCEPTING THE PROPOSAL OF JR ENGINEERING, LLC FOR DESIGN SERVICES FOR SABLE BOULEVARD IMPROVEMENTS PROJECT #23-007963 FOR THE CONTRACT AMOUNT OF TWO MILLION THREE HUNDRED SEVENTY-ONE THOUSAND THREE HUNDRED THIRTEEN DOLLARS ($2,371,313.00) AND AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE SAID CONTRACT ON BEHALF OF THE CITY
Attachments: 1. RESO 23 Sable Blvd Design 2023.10.pdf, 2. Design - Sable Blvd City Council 2023.10.pdf, 3. 343 PPT
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department of Public Works
Reference: Approving the Procurement of 23-007963 2023 Design Services for Sable Blvd
To: Mayor Gregory Mills and Members of City Council
Through: Michael P. Martinez City Manager
Prepared By: Christopher Montoya, Assistant Director of Public Works
Date Prepared: September 1, 2023
PURPOSE

Requesting City Council's approval for the procurement of 23-007963 Design Services for Sable Boulevard Improvements by awarding a contract to JR Engineering, LLC, deemed the most responsive and responsible bidder of the five (5) bids received in response to the posted solicitation, and approving the resolution giving the City Manager, or designee, authority to sign the contract. Per City Code Section 3-8-30(b): "All materials, services, and construction contracts, except as otherwise provided in this Article, with an estimated cost greater than one hundred thousand dollars ($100,000.00), shall be awarded through the formal solicitation procedure or the formal RFP process by the City Council. After due notice inviting bids, purchase orders and contracts shall be awarded to the lowest responsive and responsible bidder."

BACKGROUND/HISTORY

Formal Bids were requested from qualified Contractors for the project 23-007963 Design Sable Blvd Improvements.
The City of Brighton Public Works Department prepared a request for proposals to perform design work in multiple phases and post design services for Sable Blvd from 120th Avenue to Bromley Lane, approximately five miles of roadway.
Sable Blvd was formerly State Highway 2 owned by the Colorado Department of Transportation until 2011 when it was transferred to the City of Brighton. The roadway segment is unique with the conservation easements, agricultural, mixed with residential, and parallel to US-85. Additionally, the route is a key entry point to the City of Brighton that will serve as an icon of the history and future of the city.
The project has three phases of work including conceptual designs...

Click here for full text