File #: ID-249-15    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 8/21/2015 In control: City Council
On agenda: 9/1/2015 Final action:
Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACCEPTING THE PROPOSAL OF COMMUNICATION CONSTRUCTION AND ENGINEERING, INC. AND AWARDING THE CONTRACT FOR THE CITY OF BRIGHTON COMMUNICATION EXPANSION PROJECT, RFP #15-041, IN AN AMOUNT NOT TO EXCEED TWO HUNDRED THREE THOUSAND SIX HUNDRED FIFTY EIGHT DOLLARS AND TWENTY CENTS ($203,658.20), AND AUTHORIZING THE MAYOR TO SIGN THE CONTRACT ON BEHALF OF THE CITY AND THE CITY CLERK TO ATTEST THERETO
Attachments: 1. 15-041 Resolution, 2. 15-041 RFP Evaluation Matrix.pdf

Body
Department of Finance - Division of Procurement & Contracts
Reference: Award of Formal Proposal City of Brighton Communication Expansion Project RFP # 15-041


To: Mayor Richard N. McLean and Members of City Council

Through: Manuel Esquibel, City Manager

Prepared By: Pam Roeding, Procurement & Contracts Supervisor
Cc: Dan Frelund, Finance Director
Through: Margaret Brocklander Information and Technology Director, and Jeromy King, Assistant Information and Technology Director

Date Prepared: August 21, 2015


PURPOSE
Requesting City Council approval of a formal proposal for the City of Brighton Communication Expansion to the lowest most responsive and responsible bidder, and approving the resolution giving the Mayor authority to sign the contract. Municipal Code Section 3.08.090, ". . . . All bids and proposals in excess of $50,000 shall be awarded through formal written procedures by the city council."

BACKGROUND/HISTORY
Today's applications require more and more bandwidth and the cost for leasing these services are on the rise. To keep up with the demand it is necessary to expand the fiber network. The fiber network expansion will include the Streets & Fleets facilities, Recreation Center facilities as well as Prairie Center Parkway. The Prairie Center Parkway project will include adding street signals and the police substation on the wired network.

Formal proposals were received on August 17, 2015 at 2:00 PM; eleven (11) firms attended the mandatory pre-proposal conference with three (3) firms submitting a proposal for this project.

Firms submitting proposals:

* Communication Construction and Engineering, Inc.
* E2 Optics, LLC
* Paonia, Inc.
*
FINANCIAL IMPACT
Sufficient funding was approved in the 2015 budget for the City of Brighton Communication Expansion. The proposal from Communication Construction and Engineering, Inc.is within the budgeted amount.

STAFF RECOMMENDATION