File #: ID-264-21    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 9/8/2021 In control: City Council
On agenda: 9/21/2021 Final action:
Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACCEPTING CHANGE ORDER #2 FROM ALL STAR ENVIRONMENTAL SERVICES INC., AND APPROVING AMENDMENT #2 TO THE CONTRACT FOR PEORIA STREET DEMOLITION, PROJECT #21-006839, RAISING THE NOT TO EXCEED CONTRACT AMOUNT TO ONE HUNDRED SEVEN THOUSAND THREE HUNDRED THIRTY THREE DOLLARS AND THIRTY EIGHT CENTS, ($107,333.38), AND AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO SIGN AMENDMENT #2 ON BEHALF OF THE CITY AND THE CITY CLERK TO ATTEST THERETO
Attachments: 1. Resolution - Peoria Street Demolition

Department of Utilities

Reference: Change order to contract #21-006839 Peoria Street Demolition

 

To:                                                               Mayor Gregory Mills and Members of City Council

Through:                                          Jane Bais DiSessa, City Manager

Prepared By:                                          Amber Gibbs, Procurement & Contracts Manager

Through:                                          Scott Olsen, Stormwater Coordinator                                          

Date Prepared:                     09/01/2021

 

PURPOSE

Requesting City Council approval of a Change Order #2 and Amendment #2 to contract #20-006839 for the Peoria Street Demolition, and approving the resolution giving the City Manager authority to sign the Change Order and Amendment.  Pursuant to Municipal Code Section 3-8-175, all Change Orders in excess of $25,000.00 or 25% of the original contract value shall be approved by the City Council.

 

BACKGROUND/HISTORY

 

During the demolition process additional asbestos containing material ACM) was discovered under several other layers of flooring. The ACM was required to be removed and disposed of in accordance with all local, state and federal regulations. This ACM would not have been discoverable prior to removing the top layers of flooring. 

 

FINANCIAL IMPACT

 

Sufficient appropriation exists for the project

 

STAFF RECOMMENDATION

 

Staff recommends approval of Change Order #2 to contract #21-006839 Peoria Street Demolition in order to ensure the demolition of the structures in in compliance with local state and federal regulations.

 

OPTIONS FOR COUNCIL CONSIDERATION

 

Ø                     Approval as presented 

Ø                     Reject

 

Attachments:

Ø                     Resolution