Title: North 40th Avenue Construction Project
Attachments: 1. North 40th Ave Construction_Presentation 2026 Council Study Session.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department of Public Works
Reference: North 40th Avenue Construction Project

To: Mayor Gregory Mills and Members of City Council
Through: Michael P. Martinez, City Manager
Prepared By: Greg Labrie, Public Works Director
Date Prepared: July 28, 2026
PURPOSE
At a future regular meeting, Public Works will be requesting City Council's approval for the procurement of Construction of North 40th Avenue Roadway Segment by awarding a contract to Mid City Corporation, deemed the most responsive and responsible bidder of the ten (10) bids received in response to the published solicitation, and approving the resolution giving the City Manager, or designee, authority to sign the contract. Per City Code Section 3-8-30(b): "All materials, services, and construction contracts, except as otherwise provided in this Article, with an estimated cost greater than five hundred thousand dollars ($500,000) shall be awarded through the formal solicitation procedure by the City Council. After due notice inviting bids, purchase orders and contracts shall be awarded to the lowest responsive and responsible bidder."
BACKGROUND/HISTORY
North 40th Avenue has long been identified as an essential north-south corridor within the City's long-range transportation planning efforts. The segment between East Bridge Street and Garcia Avenue is currently incomplete, limiting mobility and increasing reliance on adjacent streets. The intersection of North 40th Avenue and East Bridge Street is currently signalized, but the roadway connection remains missing.
The proposed project will complete this missing link and improve multimodal transportation, traffic circulation, and safety in the corridor. The project will fully construct North 40th Avenue between East Bridge Street and Garcia Avenue. Major elements include:
Roadway, Pedestrian, and Bicycle Facilities
* Establish a new north-south connection from East Bridge Street to Garcia Avenue.
* Install 11-foot travel lanes, curb and gutter, sidewalks, bike...

Click here for full text