Legislation Details

File #: ID-184-26    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 6/3/2026 In control: City Council
On agenda: 6/16/2026 Final action:
Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, APPROVING THE SECOND AMENDMENT TO THE INTERGOVERNMENTAL AGREEMENT WITH THE URBAN DRAINAGE AND FLOOD CONTROL DISTRICT FOR SABLE BOULEVARD OUTFALL CHANNEL IMPROVEMENTS AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE SECOND AMENDMENT
Attachments: 1. RESO 26 2nd Am. to Sable Outfall IGA with MFHD, 2. 25-10.36B_IGA Amendment Sable Outfall, 3. MHFD IGA 2nd Amendment_Sable Outfall- CC Presentation_Final
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department of Utilities
Reference: Mile High Flood District (MHFD) IGA 2nd Amendment- Sable Outfall

To: Mayor Gregory Mills and Members of City Council
Through: Michael P. Martinez, City Manager
Prepared By: Scott Olsen, Director of Utilities
Date Prepared: June 1, 2026

PURPOSE
Requesting City Council's approval of a resolution authorizing the City Manager, or designee, to execute the 2nd Amendment to an Intergovernmental Agreement (IGA) between the City and MHFD regarding the Sable Outfall.

BACKGROUND
The Sable Outfall system will serve existing and future development in the City, including the Sable Boulevard improvements, Farmlore Development and approximately 500 acres of the Prairie Center Development. The piped portion under the Fulton Ditch (known as Phase A) has been completed by Farmlore per a reimbursement agreement previously approved by Council.

The original IGA for this phase (known as Phase B) was approved by City Council on December 16, 2025. City Council also approved the 1st Amendment on March 3, 2026, under which each party provided additional funding toward project construction.

The City and MHFD wish to add additional funding under the IGA to complete construction of the project.

Per the 1st IGA Amendment, the City and MHFD have each already contributed $1.725M for the project. Each party will now contribute an additional $600,000 to complete the project under the 2nd IGA Amendment.

Naranjo Civil Constructors was chosen by the project sponsors as the contractor for this phase of the project. Naranjo has already mobilized to the site and began work. Construction is anticipated to be complete in November 2026.

Traffic impacts to Sable Boulevard will include traffic flow in both directions controlled by a temporary traffic signal near the 148th Avenue alignment. This impact will occur over approximately 40 days beginning on or around June 15. 144th Avenue will be closed east of the intersection with Sable Boulevard for approximately 40...

Click here for full text