Skip to main content
File #: ID-231-21    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 8/5/2021 In control: City Council
On agenda: 9/7/2021 Final action:
Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, AUTHORIZING THE GRANT AGREEMENT WITH ADAMS COUNTY FOR GRANT FUNDING IN THE AMOUNT NOT TO EXCEED THREE HUNDRED EIGHTY FIVE THOUSAND DOLLARS ($385,000.00) FOR THE FOUNDERS PLAZA PHASE 2 PROJECT; AUTHORIZING THE CITY’S MATCHING OBLIGATION OF THREE HUNDRED FIFTEEN THOUSAND DOLLARS ($315,000.00); AND AUTHORIZING THE CITY MANAGER TO SIGN AND EXECUTE THE GRANT AGREEMENT
Attachments: 1. Resolution - AdCo 3-31-21 O.S. Grant - Active Grant Contract (Founders Plaza Ph.2) = 8-5-21.pdf, 2. Founders Plaza Grant Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Department of Parks and Recreation
Reference: Adams County Grant Agreement for the Founders Plaza Phase 2 Project

To: Mayor Gregory Mills and Members of City Council
Through: Jane Bais DiSessa, City Manager
Marv Falconburg, Deputy City Manager
Prepared By: Mark Heidt, Assistant Director of Parks & Recreation Development and City's Bicycle Program Coordinator
Through: Travis Haines, Director of Parks and Recreation
Date Prepared: August 5, 2021
PURPOSE
A Resolution authorizing the City of Brighton enter into a Grant Agreement with Adams County, for grant funding in the amount not to exceed $385,000.00 for the "Founders Plaza Phase 2 Project"; authorizing the City's matching obligation of $315,000.00; and authorizing the City Manager to sign and execute the Grant Agreement


STRATEGIC FOCUS AREA
Facilities, Amenities, and Open Space


BACKGROUND
Phase 1 of Founders Plaza was completed in 2020. In late July 2021, the City of Brighton received notice that it has been awarded $385,000.00 in grant funding from Adams County. The grant funding will complete the Founders Plaza and will include: enhanced colored concrete events area, trellis shelter and covered picnic tables, festoon lighting, a small activity/concert area, location for the annual Christmas tree, additional seating, and additional trees for shade.

The total cost for the "Founders Plaza Phase 2 Project" is estimated at $700,000.00. This project is the combination of both this grant request and the City's matching funds. The grant funding of $385,000.00 (55.0% of total project cost) matches the City's cash match of $315,000.00 (45.0% of total). The City Attorney has reviewed as to form the Grant Agreement and confirms that it is Adams County's standard agreement and that the terms are reasonable. The attached Resolution allows the City of Brighton, through the City Council to enter into the Agreement with Adams County and to allow the City Manager to sign and execute the Grant Agreement.


...

Click here for full text