Department of Utilities
Reference: Q4 Water Treatment Plant Update
To: Mayor Gregory Mills and Members of City Council
Through: Michael P. Martinez, City Manager
Prepared By: Marc Johns, Director of Utilities
Date Prepared: December 13, 2022
PURPOSE
To provide City Council with background and an overview of the City’s WTP as of Q4 of 2022 and a contract for soil sampling.
STRATEGIC FOCUS AREA
Supportive, Sustainable Infrastructure
Financially Responsible
BACKGROUND
The City started the process of constructing a new Water Treatment Plant in mid-year 2022. There will be quarterly updates throughout the process which will be completed in 2025. As part of the construction project there is a need for a third party for sampling. They will sample concrete, soil, and other items as needed.
STAFF RECOMMENDATION
Staff is recommending approval of the contract with Terracon for third-party sampling. Terracon is on a Master Price Agreement.
FINANCIAL IMPACT
The contract dollar amount with Terracon is in the total cost of the Water Treatment Plant project.
Attachments:
Ø Presentation