Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACTING BY AND THROUGH ITS WATER ENTERPRISE, ACCEPTING THE BID OF NORTHERN COLORADO CONSTRUCTORS/AGPROFESSIONALS, AND AWARDING THE CONTRACT FOR THE VETERANS’ PARK WATER ~QUALITY ENHANCEMENTS DESIGN-BUILD PROJECT #17005, IN AN AMOUNT NOT TO EXCEED TWO HUNDRED EIGHTY NINE THOUSAND SIX HUNDRED NINETY TWO DOLLARS ($289,692.00), AND AUTHORIZING THE MAYOR TO SIGN THE CONTRACT ON BEHALF OF THE CITY AND THE CITY CLERK TO ATTEST THERETO AND AUTHORIZING THE CITY MANAGER TO APPROVE CHANGES TO THE CONTRACT AMOUNT UP TO TWENTY PERCENT (20%) OF THE ORIGINAL CONTRACT AMOUNT
Attachments: 1. 17-016 Resolution, 2. Evaluation Matrix - RFP #17-016 FINAL SCORES, 3. RFP 17-016 MEMO Utility Project Award Recommendation

Body
Department of Utilities
Reference: Award of Formal Solicitation for Veteran's Park Water Quality Design-Build Project #17005


To: Mayor Richard N. McLean and Members of City Council

Through: Clint Blackhurst, Acting City Manager

Prepared By: Curtis Bauers, Utilities Director

Cc: Chontel Trujillo, Assistant City Manager
Jean Starr, Interim Finance Director

Date Prepared: April 24, 2017

PURPOSE
Requesting City Council approval of a formal solicitation for the Veteran's Park Water Quality Enhancement Design-Build Project #17005 to the lowest most responsive and responsible bidder, and approving the resolution giving the Mayor authority to sign the contract. Municipal Code Section 3.08.090, ". . . . All bids and proposals in excess of $50,000 shall be awarded through formal written procedures by the city council."
BACKGROUND
City of Brighton was approved last fall for a grant from the Colorado Department of Transportation Water Quality Mitigation Funding Pool in an amount of $421,978. To design and construct a stormwater quality pond at Veterans' Park. The pond will treat stormwater runoff prior to discharge to the South Platte River. Through the conditions of a previously approved IGA, Colorado Department of Transportation will reimburse the City up to four hundred twenty-one thousand nine hundred seventy-eight dollars ($421,978) to design and construct the stormwater quality pond.
Stormwater runoff from an approximately 90-acre basin currently discharges to the McCann Ditch and, ultimately, the South Platte River untreated at two locations near Veterans' Park: One location on the south side of Highway 7 and the other on the north side of the highway. This drainage basin encompasses portions of multi-family residential development, Downtown Brighton and the intersection of Highways 85 and 7.
The project is to construct a stormwater quality pond on the north side of Highway 7 and will re-direct flows from the south side of Highway 7 north...