Reference: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACTING BY AND THROUGH ITS WATER ACTIVITY ENTERPRISE, FINDING THAT GOOD CAUSE EXISTS AND THAT IT IS IN THE BEST INTERESTS OF THE CITY TO WAIVE THE FORMAL BID PROCESS FOR THE ERGER'S POND AUGMENTATION STATION CONSTRUCTION OVERSIGHT PROJECT; ACCEPTING THE PROPOSAL OF BURNS & MCDONNELL ENGINEERING COMPANY, INC., AND AWARDING THE CONTRACT FOR THE ERGER'S POND AUGMENTATION STATION CONSTRUCTION OVERSIGHT TO BURNS & MCDONNELL ENGINEERING COMPANY, INC. AS A SOLE SOURCE PROCUREMENT IN AN AMOUNT NOT TO EXCEED THREE HUNDRED EIGHTY-THREE THOUSAND FOUR HUNDRED FORTY-SIX DOLLARS ($383,446.00); AND AUTHORIZING THE MAYOR TO SIGN THE CONTRACT ON BEHALF OF THE CITY AND THE CITY CLERK TO ATTEST THERETO.
To: Mayor Kenneth J. Kreutzer and Members of City Council
Through: Philip A. Rodriguez, City Manager
Prepared By: Curtis Bauers, Director of Utilities
Date Prepared: March 12, 2018
TITLE
Award of a Sole Source Contract for the Erger's Pond Augmentation Station Construction Oversight to Burns & McDonnell Engineering Company, Inc.
PURPOSE
To request City Council to find that good cause exists and that it is in the best interests of the City to waive the formal bid process and award the contract, as a sole-source procurement, to Burns & McDonnell, the design engineer of record, for the Erger's Pond Augmentation Station Construction Oversight.
BACKGROUND/HISTORY
Burns & McDonnell Engineering Company, Inc. performed the design for the Erger's Pond Augmentation Station project. Burns & McDonnell Engineering Company, Inc. also provided bidding phase services for the procurement of the construction contractors. Due to the high complexity of the design and the project, construction oversight by the design engineer is also necessary. Construction oversight will ensure that the project will be constructed in conformance with all des...