Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACTING BY AND THROUGH ITS WATER ACTIVITY ENTERPRISE, APPROVING THE 8.3MG TANK STRUCTURAL REPAIRS CHANGE ORDER TO THE CONTRACT WITH SEH DESIGN BUILD, INC., TO AMEND THE SCOPE OF WORK IN AN AMOUNT NOT TO EXCEED FIVE HUNDRED THREE THOUSAND, SIX HUNDRED EIGHTY DOLLARS ($503,680.00); AND AUTHORIZING THE MAYOR TO EXECUTE SAID CHANGE ORDER ON BEHALF OF THE CITY AND THE CITY CLERK TO ATTEST THERETO
Attachments: 1. Reso - 8.3MG Tank Structural Repairs - CA.pdf

Body
Department of Finance - Division of Procurement & Contracts
Reference: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACTING BY AND THROUGH ITS WATER ACTIVITY ENTERPRISE, APPROVING THE 8.3MG TANK STRUCTURAL REPAIRS CHANGE ORDER TO THE WATER TANK MAINTENANCE SERVICES AGREEMENT WITH SEH DESIGN BUILD, INC., AMENDING THE SCOPE OF WORK IN AN AMOUNT NOT TO EXCEED FIVE HUNDRED THREE THOUSAND, SIX HUNDRED EIGHTY DOLLARS ($503,680.00); AND AUTHORIZING THE MAYOR TO EXECUTE SAID CHANGE ORDER ON BEHALF OF THE CITY AND THE CITY CLERK TO ATTEST THERETO


To: Mayor Kenneth J. Kreutzer and Members of City Council

Through: Philip Rodriguez, City Manager

Prepared By: Michael Woodruff, Director of Infrastructure

Date Prepared: December 12, 2018

PURPOSE
Staff is requesting City Council approval for a change order involving structural repairs of the 8.3 million gallon water tank.

Brighton Municipal Code states in Sec 3-8-175, "Change Orders:" The City Manager shall have the authority to approve individual change orders on City construction contracts greater than $2,500.00 up to $25,000.00 per change order, not to exceed the greater of $50,000.00 per contract or 25% of the original contract amount.

STRATEGIC FOCUS AREA
Financially Responsible
BACKGROUND/HISTORY
As part of the Water Tank Maintenance Services Agreement contract entered into with SEH Design/Build, Inc. in September of 2017, work under the contract scope of services for the 8.3MG tank started in November 2018. As a result of the cleaning and inspection of the tank it was discovered that the following repairs are required that are not covered under the existing contract scope of services:

1. Replace Outer Rafters (Quantity: 96)
2. Replace Inner Rafters (Quantity: 30)
3. Replace Beam Clips (Quantity: 126)
4. Replace Shell Clip/Plate (Quantity: 96)
5. Install Rafter Purlins (Quantity: 147)
6. Install Crow's Nest at Center Support
7. Incidentals required for repairs:
a. Door ...