Title: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRIGHTON, COLORADO, ACCEPTING THE PROPOSAL OF ARAPAHOE ROOFING & SHEET METAL, INC. FOR THE CITY-WIDE ROOFING PROJECT FOR THE CONTRACT AMOUNT OF ONE HUNDRED TWENTY-FIVE THOUSAND THREE HUNDRED TWENTY-NINE DOLLARS ($125,329.00) AND AUTHORIZING THE CITY MANAGER, OR DESIGNEE, TO EXECUTE THE CONTRACT ON BEHALF OF THE CITY
Attachments: 1. Resolution - Arapohoe Roofing
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Department of Facilities

Reference:                      Citywide Roofing Project

 

To:                                                               Mayor Gregory Mills and Members of City Council

Through:                                          Michael Martinez, City Manager

Prepared By:                                          Patrick Rome, Director of Facilities                     

Date Prepared:                     July 13, 2022

PURPOSE

Requesting City Council’s approval of the procurement of 22-007566 City-wide Roofing Project by awarding a contract to Arapahoe Roofing & Sheet Metal, Inc., deemed the most responsive and responsible bidder of the three (3) received as response to the posted solicitation, and approving the resolution giving the City Manager, or designee, authority to sign the contract.  Per City Code Section 3-8-90, “All materials, supplies, equipment, service and construction contracts, except as otherwise provided in this Article, with an estimated cost of greater than fifty thousand dollars ($50,000.00), shall be awarded through the formal bid process or the formal RFP process by the City Council. After due notice inviting bids, purchase orders and contracts shall be awarded to the lowest responsive and responsible bidder.”

 

STRATEGIC FOCUS AREA

 

Financially Responsible

Facilities, Amenities, and Open Space

Recognizable and Well-Planned Community

 

BACKGROUND

 

In July 2021, the City received substantial hail damage to multiple buildings, most notably the Bromley Farm and all outlying buildings on property, Main St. Creative Arts, and varying well-houses throughout the City. After insurance adjusters provided their estimates, with the help of procurement, the City requested bids for repair. We received three and followed the procurement process for choosing an appropriate bidder. Insurance has provided funds and now we must choose whom to allocate said funds to.

 

FINANCIAL IMPACT

 

Due to insurance coverage, there is no financial impact directly to the City.

 

OPTIONS FOR COUNCIL CONSIDERATION

 

                     Approve as presented

                     Reject

                     Require new proposals to be submitted

 

STAFF RECOMMENDATION

 

Staff recommends awarding the contract to Arapahoe Roofing & Sheet Metal, Inc. as the most responsive and responsible bidder for the project.

 

ATTACHMENTS

 

                     Resolution